Make Your Voice Heard! As the WI DNR and PSC Solicit Public Input Into Their Decision Making Process

Concerned Residents of Racine County will have an opportunity to add their voices and valuable input into the decision making process of both the Wisconsin Public Service Commission (PSC) and Department of Natural Resources (DNR), in regards to:

(PSC) Allowing the American Transmission Company (ATC) – Mount Pleasant Tech Interconnection Project;  and

 

 

(DNR) Allowing the City of Racine to remove an additional 7 million gallons of water per day from Lake Michigan to serve the proposed  Foxconn LCD TV manufacturing plant.

 

First – from the Journal Sentinel:

Foxconn would get $140 million electricity project, use more power than any plant in state

American Transmission Co. will seek state approval for a $140 million project to run electrical power to the huge manufacturing complex Foxconn Technology Group plans to build in Racine County.

The massive plant is expected to draw an enormous amount of power — six times more than the next-largest factory in Wisconsin, according to ATC, which declined to identify that factory.

 The project would affect the rates of residential electric customers in Wisconsin.

Before adding power lines and building the new substation, ATC will need approval from the State Public Service Commission. The utility says it will file an application with the PSC in February and ask for a decision by August.

If the commission approves the project then, construction would begin late next year on the substation and in early 2019 on the transmission lines, according to ATC. Power would start flowing by late 2019 or early 2020.

ATC is co-owned by Wisconsin utilities including We Energies, Wisconsin Public Service, Alliant Energy, Madison Gas & Electric and Superior Water, Light and Power.

To get power to Foxconn, ATC would add a second 345 kilovolt transmission circuit along 12 miles of existing lines from Pleasant Prairie north to Mount Pleasant.

That would take power to a point 1.2 miles east of the new substation. To connect the existing system to the substation, ATC would build new transmission lines, strung on 16 steel poles, 120 feet to 160 feet tall, set along an east-west corridor south of Braun Road.

 The utility would need easements through the new corridor, either by negotiating with landowners or, if necessary, acquiring the right-of-way by exercising eminent domain authority.

ATC also would build an underground line beneath Highway H to connect to a Foxconn-owned power station on the factory site.

333

Residents can voice their concerns by filing a comment with the Public Service Commission – screenshot below:

The link to the Public Service Commission Comments section is: http://apps.psc.wi.gov/vs2010/dockets/comment.aspx

Concerned Residents then need to select a Case – specifically: American Transmission Company (ATC) – Mount Pleasant Tech Interconnection Project; then click on the FILE A COMMENT prompt, which opens the window to file a comment.

From the prompt:

137-CE-188 –Application of American Transmission Company LLC to Construct and Place in Operation a New 345/138 kV Substation in the Village of Mount Pleasant, 345 kV Transmission Lines to Interconnect it With ATC’s Existing 345 kV Transmission Network, and to Construct or Reconstruct Other Lines and Facilities in the Area, to be Located in Primarily Racine and Kenosha Counties, Wisconsin

To file comments in this case fill out the information below and click on the File Comments button.

A comment may consist of the writer’s personal knowledge or personal opinions only. A reference document, newspaper article, professional journal article, white paper, study or any other prepared material not written by the person commenting is not considered a public comment, but may be referenced in a person’s comment.

333

Comments range from being supportive of MTP using Eminent Domain to confiscate private property for State purposes, granting questionably superior rights over  residents to privately owned Mega- Corporations  and being in favor of raising  rates for electricity to those who disfavor such questionably, and hastily rushed  legislatively mandated and potentially unconstitutional State actions.

Comment:
I do not understand why ANY ratepayers other than Foxconn are proposed to be charged for Foxconn’s transmission lines. This is reportedly an extremely profitable company. Part of that profitability must be massive subsidies to Foxconn paid by governments and citizens in the areas in which Foxconn locates. Please direct the ratepaying charges directly to Foxconn, the main customer for whom this transmission line is intended. If as quoted in the newspaper the cost to ratepayers is “pennies per month, pennies per year”, Foxconn can surely afford this.

I also have serious concerns about environmental impacts by Foxconn on my local environment. I would request that they abide by or exceed all current regulatory requirements and not be granted any exceptions to existing water or air quality laws.

The Comment section, which also collates the contents of many documents which are required to be filed, prior to approval, may be found at this link:

http://apps.psc.wi.gov/vs2015/ERF_search/content/searchResult.aspx?UTIL=137&CASE=CE&SEQ=188&START=none&END=none&TYPE=none&SERVICE=none&KEY=none&NON=N

From the Case Summary:

American Transmission Company (ATC) – Mount Pleasant Tech Interconnection Project
Applicant(s): American Transmission Company LLC (137)
Project Description: ATC proposes to construct new electric transmission facilities to serve the proposed Foxconn development. Facilities to be constructed include: a new Mount Pleasant Substation to provide electrical service for the Foxconn campus; two sets of double-circuit transmission lines along a 1.2-mile corridor to connect the new substation to the existing 345 kilovolt (kV) electric transmission system; an added second 345 kV transmission circuit to an existing 12-mile transmission line between the existing Racine and Pleasant Prairie Substations; modifications at the existing Racine and Elm Road Substations, and at the existing Pleasant Prairie Switchyard; and, a new 138 kV underground transmission line to connect the proposed Mount Pleasant Substation to a new substation to be owned by Foxconn. The Commission’s review of the project is limited to the proposed electric transmission facilities.
Case Coordinator: James Lepinski

Stacy Schumacher

Now Accepting Public Comments

Link: http://apps.psc.wi.gov/vs2010/dockets/content/detail.aspx?dockt_id=137-CE-188

Let your voice be heard:

From JT:

The Foxconn deal keeps getting worse and worse. From 3 billion to 4 billion and now to at least 4.5 billion of taxpayer dollars. That’s not including taxpayer water, sewer, power infrastructures and highway expansion costs.

Recently the details of the power project that Foxconn and various politicians expect you to pay for were revealed. It’s a 14-mile long, mostly above ground, high-power line with various substations and their lines.

The City and County of Kenosha wisely said no to Foxconn. That means the 10 or 12 miles of new high-powered power lines that are proposed to run across Kenosha (south to north) don’t belong there.

The lines and substations belong in Mount Pleasant and Racine County. Period. They wanted Foxconn.

Additionally, and just as important, residents of southeast Wisconsin shouldn’t have to pay the power needs of a foreign corporation that’s overflowing in money, assets and anti-suicide nets. If not stopped, these costs will be on our power bills for years to come.

The Foxcomm deal is built on faulty legal ground, bad ethics, and greed. Special laws allowing destruction of local environment, thoughtless cruel winter evictions, homes seized, and the sickening perversion of the court system to benefit a single foreign company. Now add a subsidized expensive ugly high-power line to the list.

To make your voice heard and make a comment with the Public Service Commission, contact the PSC. Call 608-266-541. Write. Or comment on webpage under “American Transmission Company (ATC) — Mount Pleasant Tech Interconnection Project” http://apps.psc.wi.gov/vs2010/dockets/comment.aspx.

Vince Mutchler

Kenosha

333

Meanwhile the DNR is getting ready to approve an application for City of Racine to extract another 7,000,000 + gallons of water daily, from Lake Michigan:

From JT:

DNR sets hearing on Foxconn water diversion

MADISON — The public will get a chance to sound off in March about Racine officials’ request to pull 7 million gallons of water per day from Lake Michigan to serve a massive Foxconn Technology plant.

The state Department of Natural Resources announced Wednesday that they’ve scheduled a public hearing on the request for March 7 in Sturtevant.

The meeting is set for 6 p.m. at the SC Johnson iMET Center, 2320 Renaissance Blvd., Sturtevant.

The agency also will take public comments on the request through March 21.

Under the Great Lakes Compact, all water diverted from Lake Michigan must be returned minus what’s lost to evaporation or what’s used for Foxconn’s manufacturing process. The city’s application estimates about 2.7 million gallons per day will be consumed and wouldn’t return to the lake. All wastewater would return to the Racine wastewater treatment plan and then the lake. Foxconn has struggled with pollution problems in China.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s